The Collegian

September 19, 2005     California State University, Fresno

Home  News  Sports  Features  Opinion  Classifieds  Gallery  Advertise  Archive  About Us  Forums

Page not found – The Collegian
Skip to Main Content
Fresno State's student-run newspaper

The Collegian

ADVERTISEMENT
Fresno State's student-run newspaper

The Collegian

Fresno State's student-run newspaper

The Collegian

Not Found, Error 404

The page you are looking for no longer exists.

Donate to The Collegian
$115
$500
Contributed
Our Goal

News

U.S. Constitution celebrated

Fraternity gunshot leads to arrests

Elevator construction near

Turnout low at two-sport event


Call him corporal

Elevator construction near

Ryan Tubongbanua / The Collegian
Construction will soon begin on the elevator cart inside the already-completed elevator shaft attached to the Psychology Building.

By Inga Lukaviciute
The Collegian

The newly built elevator structure on the Psychology Building will soon house its second half, the elevator cart, as the process to finish this elevator is about to start.


The biding for a contractor to design and build the elevator cart will start in the next few days and the elevator should be functioning by next semester, said Gary Wilson, director of plant operations.


Originally the elevator was to be completed by May 2005, according to the university Web site, but is currently only half-finished, Wilson said.


The contractor L.C. Nelson, who built the elevator structure, was contracted to design and build the cart as well, but because of delay of the project, it was decided to pull the elevator cart out of the contract so that other landscaping projects in the area could be finished on time and the university would not have to extend the original contract, Wilson said.


Rain was one of the major factors that delayed construction, as it was difficult to drain the area. Another factor was utility lines, since more were found when the excavating started than the drawings showed, Wilson said. It was not a problem but the elevator structure had to be moved up four feet. Instead of 20 feet wide it had to be redesigned to be 24 feet. Consequently, the elevator cart had to be redesigned as well.


At the end of the semester there were many other projects to finish and the elevator did not get the time it needed, Wilson said.


The area around the elevator will become a construction zone once the building starts, Wilson said. The exit by the elevator will be closed and will only serve as an emergency exit. There will be no more digging since the construction will take place inside the elevator building, Wilson said.


There is a possibility the project may not start until a break, Wilson said, if they receive complaints about the noise.


The construction of the elevator began in January 2005 along with the remodeling of the second floor of the building.

Comment on this story in the News forum >>